Warren would like to get a crew on Friday and Saturday to remove the carpet and linoleum from the Bruce Hall slab before the building is demolished next week. The new building will be built on top of the existing concrete slab. The demolition crew will dispose of the carpet and linoleum only if they have been ripped off the slab.

If the carpet is still on the slab during demolition, we'll have to remove it later, and pay extra to dispose of it. We don't want that cost.

Selective demolition continued Tuesday and Wednesday, with much of the tile floor removed in the pre-school building -- and some still to go. If you are there on Friday or Saturday, you could help with that, too.

The walkway roof connecting the pre-school to the narthex was removed Wednesday, and the gas was shut off in the pre-school building and Bruce Hall.

Know anyone who could use a 5-year-old gas furnace? Emmanuel now has one that we can't use anymore. We'd like to find a good home for it.

Remember, comment on this blog item to let us know if and when you'll be able to help. The construction manager will be checking the comments to see who to expect and when.