Monday, December 1, 2008

The walls come tumblin' down

Well, we had selective demolition last week, finishing up Sunday afternoon.

Monday morning general demolition started with the pre-school building. By noon only the women's restroom and the chimney were left standing.

Here's a new slideshow of photos. Click on the arrow to get it started. Larry contributed several photos at the beginning and end, since he was there all day and I just stopped in for a while in the morning.



Demolition of Bruce Hall should be complete by the end of Tuesday. After that, excavation begins.

Warren needs some help putting up plastic safety fences around the construction site.

Remember, please click on COMMENTS below this item to let us know if and when you'll be able to help. The construction manager will be checking the comments to see who to expect and when.

No comments:

Post a Comment

Please let us know if you want to work on this project and when you are available.