Monday, September 14, 2009

Official capacity

The preschool opened today in their wonderful new classrooms.

Pastor Steve and Rena' were both moved into their new offices in the main building over the weekend. The pastor has a lot of unpacking to do today.

Lots of construction related equipment and supplies continue to occupy space in the various storage areas and in the middle of the fellowship area. Dozens of small projects remain to be completed here and there throughout the building, including a multitude of cleaning tasks.

The mobiles are virtually empty. Deconstruction has begun on the ramp from the preschool mobile and can begin now on the ramp and stairs from the office mobile unit, so that both can be removed from the site.

We're aiming for a worship service in the new building on Sunday, Sept. 26.