Sue's photos and report from Thursday:
After the carpet job was complete, Judy Kuiken vacuumed the whole area on Thursday. Then the pews, communion table and pulpit were moved back in. Bill Sharp had taken the crosses home to clean and renew their finish, and had reinstalled them on Wednesday. They look wonderful, and are now back in their place of honor.

Thursday, Warren put the "crash bars" on the front doors. After that was done, Bill and Paul sanded them to ready them for the finish application.
[Note: Particle board covers the areas in the doors where the glass will go. Glass will replace these panels someday soon.]

When I left, Warren had installed the vinyl in the kitchen and was helping install the triple sink and grease trap.

This week has been very busy at church. The goal is to get the Certificate of Occupancy. Then, Pastor Steve and Rena' can move into the new offices. Then, the Mobile Minis can be removed from the property. It will probaby be a week or two before we will hold Sunday services in the sanctuary
.